757 Coastal Remodeling
757 Coastal RemodelingScope of Work & Estimate
Change Work Order CO-0004 · Estimate #1414
213 South Birdneck Rd, Virginia Beach, VA
$3,570.75Change Work Order CO-0004 · 5 Powerpost Piers with the foundation repair · Crawlspace regrade · 10% discount applied
213 South Birdneck Rd, Virginia Beach, VA · Keymworld LLC
Added to the accepted Estimate #1414 ($20,000.00) · project total $23,570.75
Print / Save PDF — Change Work Order CO-0004 View the accepted Estimate #1414
Change Work Order valid until October 16, 2026
Included Scope of Work — Change Work Order CO-0004
FOUNDATION
Powerpost Piers — Foundation (Both Units)5 posts
  • Five (5) power posts — concrete piers with metal jacks — installed with the foundation repair on both units.
  • Each post is set on its own concrete footing and shimmed tight to the beam.
  • Not included in this line: footings beyond the five posts; any work outside the crawlspace.
Miscellaneous — Crawlspace RegradeIncluded · no charge
  • The crawlspace is regraded level and the loose soil pulled back from the footing.
  • Soil stays on site — nothing is hauled away from the house.
  • Not included in this line: removing soil from the property; new drainage.
Itemized — Change Work Order CO-0004
ServicePrice
Powerpost Piers — Foundation (Both Units)
Five (5) power posts (concrete piers with metal jacks) installed with the foundation repair on both units — set on their own concrete footings and shimmed tight to the beam. $793.50 each.
$3,967.50
Miscellaneous — Crawlspace Regrade
Crawlspace regraded level, loose soil pulled back from the footing — soil stays on site, nothing is hauled away from the house.
$0.00
Customer Discount -$396.75
Change Order Total$3,570.75
Project Totals
Accepted Estimate #1414
$20,000.00
Foundation repair on both units — already accepted, unchanged
This Change — CO-0004
$3,570.75
5 power posts with the foundation repair · crawlspace regrade · 10% discount applied
Project total once this change is accepted: $23,570.75 · Approval: sign and return the Change Work Order, or reply “accepted”. The payment terms of the accepted Estimate #1414 are unchanged. Check is a preferred method · Pay by credit card: request.plastiq.com/pay-tidewater-home-improvement-llc (Virtual Affirm credit card not eligible)
Site Photos — Before Work (106)
Terms & Clarifications

This is a change: Change Work Order CO-0004 on the accepted Estimate #1414 at 213 South Birdneck Rd, Virginia Beach — it is not a new estimate of the whole project.

Scope: five (5) power posts (concrete piers with metal jacks) installed with the foundation repair on both units — set on their own concrete footings and shimmed tight to the beam; and the crawlspace regraded level, with the loose soil pulled back from the footing. Soil stays on site — nothing is hauled away from the house.

Pricing: this change $3,967.50, less the 10% customer discount of $396.75 — change amount $3,570.75, added to the accepted Estimate #1414 total of $20,000.00, for a project total of $23,570.75 once this change is accepted.

Unchanged: everything in the accepted Estimate #1414 stays exactly as accepted — its scope, pricing, exclusions and warranty. Nothing already covered by Estimate #1414 is re-charged here.

Approval: this change is not accepted until it is signed. Sign the Change Work Order and send it back, or reply “accepted”.

Notes: the jobsite is left clean once the work is complete. Unforeseen concealed conditions are documented and presented for written approval before that work proceeds.

Warranty: one (1) year workmanship on the foundation repair, framing, subfloor and removal work from substantial completion.

Not included: anything outside the scope above; new flooring installation; roofing; windows, exterior doors and siding; insulation, drywall and painting; cabinets and countertops; appliances, plumbing, electrical and HVAC; the 3rd structure on the property.